New Venture, Inc. has received a contract for 8 units of a new product. The contract is a cost-plus contract, with the total to be received equal to the total labor cost + 20%. New Venture found that the first unit of a new product required 120 hours to complete. The second unit was completed using only 114 hours. New Venture believes that the rate of learning that was observed will continue for all 8 units of the contract. The labor wage paid is $25/hour. The following factors are available for various rates of learning: 80% learning, b = -0.3219; 85%, b = -0.2345; 90%, b = -0.1520; 95%, b = -0.0740.
Required:
(a.) What will the total labor cost be for the contract?
(b.) What will the total fee be for the contract?
Correct Answer:
Verified
The learning rate is 114 hrs/120 hr...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q107: Yates Corp. wants to develop a
Q108: Clough Company is interested in establishing
Q109: Market Products, Inc., has found that
Q110: Barnard Enterprises had an average cost of
Q111: Argo Company ran a regression analysis
Q113: Yates Corp. wants to develop a
Q114: The Ornate Company produces a single product
Q115: Iowa Enterprises had an average cost of
Q116: Describe the engineering method of cost estimation.
Q117: Clough Company is interested in establishing
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents