Thane Company Is Interested in Establishing the Relationship Between Electricity
Question 80
Question 80
Multiple Choice
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours2,5002,9001,9003,1003,8003,3004,1003,5002,0003,7004,7004,200Electricity Costs$18,40021,00013,50023,00028,25022,00024,75022,75015,50026,00031,00027,750
Summary Output Regression Statistics Multiple R R Squuare Adjusted R 2 Standard Error Observations 0.9650.9320.9251,425.1812.00
Intercept Machine Hours Coefficients 3,726.885.77 Standard Error 1,682.820.49 t Stat 2.2111.7 P-value 0.050.00 Lower 95%(22.69) 4.67 Upper 95%7,476.456.87
- If the controller uses the high-low method to estimate costs, the cost equation for electricity costs is: