The Altoona Manufacturing Company Collected the Following Information (In Days)

Question 110

Essay

The Altoona Manufacturing Company collected the following information (in days) for July, August, and September:
 July  August  Septernber  Transporting product 2.03.02.0 Processing product 5.07.07.0 Inspectirng product 0.50.81.0 Storing product 1.03.04.0\begin{array} { | l | r | r | r | } \hline & \text { July } & \text { August } & \text { Septernber } \\\hline \text { Transporting product } & 2.0 & 3.0 & 2.0 \\\hline \text { Processing product } & 5.0 & 7.0 & 7.0 \\\hline \text { Inspectirng product } & 0.5 & 0.8 & 1.0 \\\hline \text { Storing product } & 1.0 & 3.0 & 4.0\\\hline\end{array}
Required:
a. Calculate the manufacturing cycle efficiency for July, August, and September.
b. Assume October's processing time will be the same as September. If Altoona's target for manufacturing cycle efficiency is 65%, what will be October's target for manufacturing cycle time?

Correct Answer:

verifed

Verified

a.July: [5.0/(2.0 + 5.0 + .5 +...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents