The Falisari Company Collected the Following Information (In Days) -
What Is the Manufacturing Cycle Time?
A) 65 Days

Question 76

Multiple Choice

The Falisari Company collected the following information (in days) :
 Inspecting product 4 Transporting product 14 Storing product 20 Manufacturing product 65\begin{array} { | l | r | } \hline \text { Inspecting product } & 4 \\\hline \text { Transporting product } & 14 \\\hline \text { Storing product } & 20 \\\hline \text { Manufacturing product } & 65 \\\hline\end{array}
-
What is the manufacturing cycle time?


A) 65 days.
B) 34 days.
C) 103 days.
D) 85 days.