Brutus Construction
Brutus Construction Started Work on a New High

Question 136

Essay

Brutus Construction
Brutus Construction started work on a new high rise building on January 1, 2019, The project completion date is December 2021. The contract price is $54,000,000. The following are the actual costs incurred and estimates of cost to complete the project.
 Years  Actual costs incurred  Estimated costs to complete 2019$15,000,000$30,000,000202022,500,00022,500,000202117,500,0000\begin{array} { r c c } \text { Years } & \text { Actual costs incurred } & \text { Estimated costs to complete } \\2019 & \$ 15,000,000 & \$ 30,000,000 \\2020 & 22,500,000 & 22,500,000 \\2021 & 17,500,000 & - 0 -\end{array}
-Refer to Brutus Construction. Calculate gross profit or loss for 2019, 2020 and 2021 using the percentage of completion method.

Correct Answer:

verifed

Verified

None...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents