Camey Construction enters into a long-term fixed price contract to build an office building for $5,000,000. In the first year of the contract Camey incurs $1,400,000 of cost and the engineers determined that the remaining costs to complete the project are $2,500,000. Camey billed $4,000,000 and collected $1,000,000 in year 1. Refer to Camey Construction. How much gross profit should Camey recognize in Year 1 assuming the use of the percentage of completion method? (Round any intermediary percentages to the nearest hundredth percent, and round your final answer to the nearest whole dollar.)
A) $394,900
B) $2,600,000
C) $525,000
D) $1,400,000
Correct Answer:
Verified
Q38: Explain the similarities and differences between the
Q45: The Billings on Construction in Progress is
Q46: The Construction in Progress account is what
Q125: Craft Construction
Craft Construction entered into a
Q126: Gleason Construction enters into a long-term fixed
Q130: At the beginning of 2019 Premier
Q131: Gordo Yachts
At the beginning of 2019
Q132: Gleason Construction enters into a long-term fixed
Q133: Tullis Construction enters into a long-term fixed
Q134: When accounting for revenue for a long-term
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents