Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,700,000. In the first year of the contract Tullis incurs $2,100,000 of cost and the engineers determined that the remaining costs to complete the project are $4,900,000. Tullis billed $4,000,000 in year 1 and collected $3,500,000 by the end of the end of the year. How much gross profit should Tullis recognize in Year 1 assuming the use of the completed-contract method?
A) $0
B) $1,900,000
C) $3,700,000
D) $7,000,000
Correct Answer:
Verified
Q27: The cumulative percentage of completion is found
Q45: The Billings on Construction in Progress is
Q56: Journal entries for the percentage-of-completion method are
Q77: The major difference between the percentage-of-completion method
Q115: Tullis Construction enters into a long-term fixed
Q118: Penn sells cameras. On August 1, a
Q121: What happens to the Construction in Progress
Q122: At the beginning of 2019 Gordo
Q123: Gleason Construction enters into a long-term fixed
Q125: Craft Construction
Craft Construction entered into a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents