Calculate the NPV of the following project using a discount rate of 12%: Yr 0 = -$500; Yr 1 = -$50; Yr 2 = $50; Yr 3 = $200; Yr 4 = $400; Yr 5 = $400
A) $15.00
B) $61.22
C) $118.75
D) $208.04
E) $269.21
Correct Answer:
Verified