An organisation's accountant is estimating next period's total overhead costs. She performed two regression analyses, one based on direct labour hours and the other based upon machine hours. The results were: Total overhead = $150,000 + $4 x direct labour hours
Adjusted R-square = 0.83
Total overhead = $130,000 + $5 x machine hours
Adjusted R-square = 0.77
For the next period the accountant anticipates using 28,000 direct labour hours and 26,000 machine hours. Based upon this information, what is the best estimate for overhead for the next period?


A) $262,000
B) $260,000
C) $254,000
D) $270,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents