If estimated production overhead in the painting department is $120,000 and actual overhead is $116,000 and estimated machine hours in the painting department are 30,000 hours and actual machine hours are 28,000 hours, the under or over applied overhead is:
A) $12,000 over applied
B) $4,000 under applied
C) $4,000 over applied
D) $8,000 under applied
Correct Answer:
Verified
Q99: If the percentage of completion is over
Q100: In which order do the following activities
Q101: The following information is available for
Q102: In a job costing system the accounting
Q103: In a job costing system the accounting
Q105: The correct order for the steps in
Q106: If the balance of over or under
Q107: The journal entry; debit work in process
Q108: Master House Ltd uses a job costing
Q109: In a job costing system the accounting
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents