Aztec Bromac budgeted the following cost standards for the current year: Direct materials = 2.8 kilos per unit @ $3.00 per kilo
Direct labour = 1.5 hours per unit @ $6 per hour
Actual production and costs were as follows:
Units produced = 3,600
Direct materials used = 9,000 kg.
Direct materials purchased = 10,000 kg. @ a cost of $29,000
Direct labour incurred = 4,000 hours at a cost of $26,000
The labour price variance was:
A) $600 F
B) $6,400 U
C) $2,000 F
D) $2,000 U
Correct Answer:
Verified
Q96: Managers should consider sales levels when investigating
Q97: The fixed overhead spending variance can be
Q98: Consider the following data for Morethanmoney Ltd.
Q99: The use of standards allows managers to:
A)
Q100: Assume the additional information for Morethanmoney Ltd.
Q102: Scenesay Ltd is a capital intensive
Q103: The journal entry to record the
Q104: Scenesay Ltd is a capital intensive
Q105: Aztec Bromac budgeted the following cost standards
Q106: Aztec Bromac budgeted the following cost standards
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents