Allowable risk of overreliance is the risk that the auditor is willing to take of accepting a control as effective, or a rate of monetary misstatements as tolerable, when the true population deviation rate is greater than the tolerable deviation rate.
Correct Answer:
Verified
Q26: It is equally acceptable under professional auditing
Q51: An auditor using nonstatistical sampling cannot formally
Q85: If a particular internal control is not
Q86: In systematic sample selection, the interval is
Q87: Even when non-sampling risk is zero, there
Q88: While performing a substantive test of details
Q91: Difference estimation, ratio estimation, and mean-per-unit estimation
Q92: The method used to measure the estimated
Q94: Except for the definition of what is
Q95: Non-sampling error occurs when audit tests do