Multiple Choice
Table 3.13
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 3.13,what is the critical path and the expected completion time for this project?
A) A-C-E-G; 33 weeks
B) B-D-F-G; 33 weeks
C) B-C-E-G; 35 weeks
D) B-C-F-H; 34 weeks
Correct Answer: