Table 3.5 Activity A B C D E F G Immediate Predecessor(s) ⋯⋯ A,B A C D,E C Time (weeks) 6326228 -Using Table 3.5,what is the critical path of this project?
A) A-C-G B) B-C-G C) A-C-E-F D) A-D-F
Correct Answer: