Table 7.3
A company uses a kanban system. The daily demand for part A is 4000 units. The average waiting time for a container of parts is 0.2 day. The processing time for a container of part A is 0.8 day, and a container holds 300 units.
-Use the information in Table 7.3.How many kanban containers would be required if a 15 % efficiency factor is used?


A) 10 or less
B) 11 or 12
C) 13 or 14
D) 15 or more