Table 7.3
A company uses a kanban system. The daily demand for part A is 4000 units. The average waiting time for a container of parts is 0.2 day. The processing time for a container of part A is 0.8 day, and a container holds 300 units.
-Use the information in Table 7.3.How many kanban containers would be required if a 15 % efficiency factor is used?
A) 10 or less
B) 11 or 12
C) 13 or 14
D) 15 or more
Correct Answer:
Verified
Q45: _ refers to the goal of having
Q52: Any deviation from the optimum process that
Q56: Although small lot sizes are beneficial to
Q59: For firms along the supply chain, two
Q60: The main focus of lean systems in
Q69: The _ method produces the item when
Q72: A(n) _ assembly line produces a mix
Q79: _ are operating systems that are designed
Q107: Table 7.2
A manufacturer using a kanban system
Q110: Table 7.2
A manufacturer using a kanban system
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents