Table 7.1
A toy company uses a kanban system to make a metal fastener that is a component of several toys. The waiting time for a container of the fasteners during production is 0.25 day; average processing time is 0.15 day per container. Each container holds 200 fasteners. The company uses 2000 fasteners a day in the production of its product.
-Use the information in Table 7.1.Using an efficiency factor of 5 %,calculate the number of kanban containers needed for the fastener.
A) 3 or less
B) 4 or 5
C) 5 or 6
D) the next person or machine to use or further the current process 7 or more
Correct Answer:
Verified
Q7: _ is the philosophy that waste can
Q75: A(n) _ is a card used to
Q93: With respect to quantities,which characteristic of JIT
Q94: When implementing a JIT system,
A) managers can
Q95: Which of the following will result if
Q96: Which of the following would not be
Q97: When a push system is replaced by
Q99: Mixed model production requires
A) computer scheduling.
B) special-purpose
Q100: Implementing a JIT system
A) has the advantage
Q102: Table 7.1
A toy company uses a kanban
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents