Table 4.2
High Tech, Inc. is producing two types of products: A and B. Both are produced at the same sawing operation. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic) . The demand forecasts, batch sizes (units/batch) , processing times (hr/unit) , and setup times (hr/batch) follow.
The sawing machines operate on two 8-hour shifts, 5 days per week, and 50 weeks per year. The manager wants to maintain a 10 percent capacity cushion.
-Using the information from Table 4.2,what is the minimum total number of hours required of sawing equipment for the next year?
A) less than 85,000 hours
B) more than 85,000 but less than 95,000
C) more than 95,000 but less than 105,000
D) more than 105,000 hours
Correct Answer:
Verified
Q81: Table 4.2
High Tech, Inc. is producing
Q82: A company's production facility,consisting of two
Q83: Table 4.4
Mr. Lee is considering a
Q84: The Northern Manufacturing Company is producing
Q85: Up,Up & Away is a producer
Q87: Table 4.2
High Tech, Inc. is producing
Q88: Musk L.Flexor owns a hot tub
Q89: Table 4.3
The North Bend Manufacturing Company
Q90: Table 4.4
Mr. Lee is considering a
Q91: John Owen owns a drugstore that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents