Conversion Factors for the Cumulative Average Number of Direct Labor
Question 23
Question 23
Multiple Choice
Conversion Factors for the Cumulative Average Number of Direct Labor Hours per Unit 80% Learning Rate ( n= cumulative production) n1234567891011121314151617181.000000.900000.834030.785530.747550.716570.690560.668240.648760.631540.616130.602240.589600.578020.567370.557510.548340.53979n1920212223242526272829303132333435360.537180.524250.517150.510450.504100.498080.492340.486880.481670.476680.471910.467330.462930.458710.464640.450720.446940.44329n37383940641282565126007008009001,0001,2001,4001,6001,8002,0000.439760.436340.433040.429840.373820.302690.244050.196220.186610.177710.170340.164080.158670.149720.142540.136600.131550.1272090% Learning Rate ( n= cumulative production) n1234567891011121314151617181.000000.950000.915400.889050.867840.850130.834960.821720.809980.799450.789910.781200.773200.765800.758910.752490.746460.74080n1920212223242526272829303132333435360.735450.730390.725590.721020.716660.712510.708530.704720.701060.697540.694160.690900.687750.674710.681770.678930.676170.67350n37383940641282565126007008009001,0001,2001,4001,6001,8002,0000.670910.668390.665950.663570.620430.560690.505860.455940.445190.434960.426290.418780.412170.400970.391730.383900.377110.37114
-The production for a new product follows: Month 1234 Units 4567 The first unit will take 2,000 hours to produce and the learning rate is 90 percent.Currently,the company employs 40 workers,who each work 200 hours regular time per month.In which months will overtime be needed for the production schedule shown? Refer to the copy of Table G.1 above.
A) Month 4 only B) Months 3 and 4 only C) Months 1 and 2 only D) Month 1 only
Correct Answer:
Verified
Unlock this answer now Get Access to more Verified Answers free of charge