Question 130

Essay

Hayden,Inc.produces two different products,Product A and Product B.Hayden uses a traditional volume-based costing system in which direct labor hours are the allocation base.Hayden is considering switching to an ABC system by splitting its manufacturing overhead cost across three activities: Engineering,Manufacturing,and Inspection.The cost of each activity and usage of the activity drivers are as follows:
Hayden,Inc.produces two different products,Product A and Product B.Hayden uses a traditional volume-based costing system in which direct labor hours are the allocation base.Hayden is considering switching to an ABC system by splitting its manufacturing overhead cost across three activities: Engineering,Manufacturing,and Inspection.The cost of each activity and usage of the activity drivers are as follows:    Hayden manufactures 10,000 units of Product A and 5,000 units of Product B per month. Required: a.Calculate the predetermined overhead rate under the traditional costing system. b.Calculate the activity rate for Engineering. c.Calculate the activity rate for Manufacturing. d.Calculate the activity rate for Inspection. e.Calculate the indirect manufacturing costs assigned to each unit of Product A under the traditional costing system. f.Calculate the indirect manufacturing costs assigned to each unit of Product B under the traditional costing system. g.Calculate the indirect manufacturing costs assigned to each unit of Product A under the ABC system. h.Calculate the indirect manufacturing costs assigned to each unit of Product B under the ABC system. i.Which product is under-costed and which is over-costed under the volume-based cost system compared to ABC? Hayden manufactures 10,000 units of Product A and 5,000 units of Product B per month.
Required:
a.Calculate the predetermined overhead rate under the traditional costing system.
b.Calculate the activity rate for Engineering.
c.Calculate the activity rate for Manufacturing.
d.Calculate the activity rate for Inspection.
e.Calculate the indirect manufacturing costs assigned to each unit of Product A under the traditional costing system.
f.Calculate the indirect manufacturing costs assigned to each unit of Product B under the traditional costing system.
g.Calculate the indirect manufacturing costs assigned to each unit of Product A under the ABC system.
h.Calculate the indirect manufacturing costs assigned to each unit of Product B under the ABC system.
i.Which product is under-costed and which is over-costed under the volume-based cost system compared to ABC?

Correct Answer:

verifed

Verified

a.$2.00 = ($600,000 + $800,000 + $200,00...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents