Frederick Brooks,Jr.observed that adding manpower to a late software project makes completion faster.
Correct Answer:
Verified
Q19: Henry L.Gantt developed Gantt charts almost 100
Q20: The task name should be unique in
Q21: Progress reports may be given verbally to
Q22: A _ involves breaking a project down
Q23: The three legs of a project triangle
Q25: The task duration is the same as
Q26: If the project manager fails to plan,staff,organize,supervise,communicate,motivate,evaluate,direct,and
Q27: The first step in the creation of
Q28: Project planning,an activity of a project manager,_.
A)
Q29: Project reporting,an activity of a project manager,_.
A)