The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,the probability that the project will take longer than 33 weeks to complete is approximately
A) 0.19.
B) 0.32.
C) 0.68.
D) 0.81.
Correct Answer:
Verified
Q70: The following table of probabilistic time estimates
Q71: A project consists of the following four
Q72: The following table of probabilistic time estimates
Q73: A project consists of the following activities:
Q74: The following table of probabilistic time estimates
Q77: The following table of probabilistic time estimates
Q78: CPM/PERT The key elements of project control
Q79: The following table of probabilistic time estimates
Q80: A project consists of the following four
Q88: Which of the following statements is generally
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents