The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,the variance of the project's total completion time is
A) 5.472 .
B) 5.222 .
C) 4.872 .
D) 3.752 .
Correct Answer:
Verified