The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,the expected time to complete the project is
A) 34.17 weeks.
B) 33.23 weeks.
C) 31.00 weeks.
D) 21.67 weeks.
Correct Answer:
Verified
Q44: In general,the latest finish time for an
Q47: In general,the earliest finish time for an
Q55: For an activity-on-node (AON)network,
A)arrows represent activities and
Q58: A project consists of the following activities:
Q62: The following table of probabilistic time estimates
Q63: A project consists of the following four
Q64: The following table of probabilistic time estimates
Q65: The following table of probabilistic time estimates
Q66: A project consists of the following four
Q72: The slack time for an activity can
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents