The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.2 Using Table 9.2,the expected time to complete activity A is
A) 5.00 weeks.
B) 7.33 weeks.
C) 7.67 weeks.
D) 8.00 weeks.