A project consists of the following activities:
Table 9.1
-Using Table 9.1,the critical path for this project consists of activities
A) A-B-C-D-E-F.
B) A-C-E-F.
C) A-B-C-F.
D) A-B-D-F.
Correct Answer:
Verified