A work centre had planned outputs of 10,15,13, and 20 hours with actual outputs of 12, 14, 13, and 18 hours. The cumulative deviation in output is
A) 0.
B) 1.
C) -1.
D) 58.
E) unable to determine with given information.
Correct Answer:
Verified
Q27: If job 5 takes 3,4 or 5
Q48: If an assignment problem consists of 5
Q49: Which of the following files tracks work
Q49: There are two jobs to be assigned
Q50: Which of the following dispatching rules ordinarily
Q52: Five jobs are waiting to be
Q55: If an assignment problem consists of 6
Q55: EDD stands for
A) earliest due date.
B) earliest
Q56: A work centre had actual input of
Q71: Orders are processed in the sequence in