A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before day (rounded to nearest day) .
A) 98
B) 112
C) 120
D) 124
E) 220
Correct Answer:
Verified
Q61: A local project being analyzed by PERT
Q62: An activity on a PERT network has
Q63: A project whose critical path has an
Q64: A contractor's project being analyzed by PERT
Q65: _ is an organization formed to ensure
Q67: An activity on a PERT network has
Q68: A PERT project has 45 activities, 19
Q69: If an activity whose normal duration is
Q70: Two critical path activities are candidates
Q71: Two critical path activities are candidates
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents