A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, the probability that the project will be completed in 88 days or less is
A) 0.0228
B) 0.3446
C) 0.6554
D) 0.9772
E) 18
Correct Answer:
Verified