A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, the probability that the project will be completed in 95 days or less is
A) -0.4
B) 0.0228
C) 0.3444
D) 0.9772
E) 4.2
Correct Answer:
Verified
Q48: A simple CPM network has three activities,A,B,and
Q56: The critical path for the network
Q57: Which of the following statements concerning CPM
Q60: Which of the following statements regarding PERT
Q62: An activity on a PERT network has
Q63: A project whose critical path has an
Q64: A contractor's project being analyzed by PERT
Q65: _ is an organization formed to ensure
Q66: A project whose critical path has an
Q90: In a PERT network, non-critical activities that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents