A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E.
A) There are two paths in this network.
B) There are four paths in this network.
C) There are five paths in this network.
D) There are 25 paths through this network.
E) There is no critical path in this network.
Correct Answer:
Verified
Q39: A project organization
A) is effective for companies
Q40: WBS stands for which of the following
Q41: The critical path for the network
Q43: The critical path for the network
Q43: The Beta distribution is used in project
Q45: The critical path for the network
Q46: Which of the following statements regarding PERT
Q49: A project being analyzed by PERT has
Q79: Which of the following statements concerning CPM
Q90: In a PERT network, non-critical activities that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents