Which of the following statements regarding CPM is true?
A) The critical path is the shortest of all paths through the network.
B) The critical path is that set of activities that has positive slack.
C) Some networks have no critical path.
D) All activities on the critical path have their LS equal to the maximum EF of all immediate predecessors.
E) The critical path is that set of activities that has negative slack.
Correct Answer:
Verified
Q11: A code of ethics especially for project
Q31: Which of the following statements regarding project
Q34: The project organization works best when which
Q35: Ethical issues that may arise in projects
Q39: A project organization
A) is effective for companies
Q40: WBS stands for which of the following
Q41: The critical path for the network
Q43: The critical path for the network
Q48: A simple CPM network has three activities,A,B,and
Q90: In a PERT network, non-critical activities that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents