The main difference between PERT and CPM is that
A) PERT is more accurate than CPM.
B) PERT assumes that activity durations are known.
C) PERT ignores activity costs.
D) CPM assumes that activity durations can vary.
E) they differ in terminology and in the construction of the network.
Correct Answer:
Verified