Which of the Following Statements Regarding Project Management Is False

Question 31

Multiple Choice

Which of the following statements regarding project management is false?


A) Gantt charts give a timeline for each of a project's activities, but they do not adequately illustrate the interrelationships between the activities and the resources.
B) A project organization works best for a project that is temporary but critical to the organization.
C) A project organization works well when the work contains simple, independent tasks.
D) Gantt charts and PERT/CPM are never used together.
E) All of the above are false.