A defence contractor has just started producing turbines for a new government contract. The first turbine took 7000 hours to produce. If the learning curve is 90%, how long will it take to produce the 10th turbine? (Use at least three decimals in the exponent if you use the logarithmic approach.)
A) less than 4800 hours
B) from 4800 to 4900 hours
C) from 4900 to 5000 hours
D) from 5000 to 5100 hours
E) over 5100 hours
Correct Answer:
Verified
Q1: The fact that human activities typically improve
Q21: The first unit of a product took
Q25: The first unit of a product took
Q38: Which of the following statements comparing learning
Q39: If it took 1000 hours to produce
Q42: A defence contractor has just started producing
Q43: A company negotiates a price for two
Q44: The first unit of a product took
Q45: The first unit of a product took
Q46: The first unit of production took 10
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents