The process capability measures Cp and Cpk differ because
A) only one ensures the process mean is centered within the limits.
B) Cp values above 1 indicate a capable process, Cpk values above 2 indicate a capable process.
C) both are identical.
D) Cp values for a given process will always be greater than or equal to Cpk values.
E) Cpk values for a given process will always be greater than Cp values.
Correct Answer:
Verified
Q61: A Cpk index of 1.00 equates to
Q62: The local newspaper receives several complaints
Q63: Which of the following statements on acceptance
Q65: Acceptance sampling is usually used to control
A)
Q66: An acceptance sampling plan's ability to discriminate
Q67: A nationwide parcel delivery service keeps
Q68: A Cp of 1.33 indicates how many
Q69: A manufacturer uses statistical process control to
Q71: An operating characteristic (OC) curve describes
A) how
Q110: Acceptance sampling:
A)may involve inspectors taking random samples
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents