In 2016,Modern Construction Company Entered into a Contract to Construct

Question 88

Essay

In 2016,Modern Construction Company entered into a contract to construct a building for $5,000,000.The estimated cost to complete the building is $4,000,000 and the project will be completed in 2017.Modern incurred actual construction costs of $1,600,000 and $1,800,000 in 2016 and 2017,respectively.How much gross profit is recognized using the percentage-of-completion method in 2016 and 2017?

Correct Answer:

verifed

Verified

blured image 2016: (1,600,000 / 4,000,000)...