Solved

A Court Will Not Enforce a Liquidated Damages Clause When

Question 120

Multiple Choice

A court will not enforce a liquidated damages clause when:


A) the amount specified is too small and considered to be unfair.
B) the amount of actual damages is significantly greater than the amount specified as liquidated damages.
C) the amount was agreed to by the parties prior to the existence of an actual breach.
D) the amount is so large that it is viewed as a penalty.
E) the actual damages are difficult to determine and compare to the amount specified as liquidated damages.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents