Architects LLC enters into a contract with Barns & Silos Inc. to provide designs for a certain number of farm buildings. Architects provides fewer than half of the designs by the time specified in the contract because the firm is busy with other projects. Architects' performance is most likely
A) a material breach.
B) a minor breach.
C) a reasonable breach.
D) no breach.
Correct Answer:
Verified
Q48: Bottling Company enters into a contract with
Q51: Iggy and Jon sign a contract by
Q52: Restoration Inc. enters into a contract to
Q52: Juan and Isidro enter into a contract
Q53: Gina enters into a contract to buy
Q55: Security Company enters into a contract with
Q56: Debt Collection Service enters into a contract
Q58: Dairy Farm enters into a contract with
Q60: Inez hires Josh to paint her portrait
Q65: Leah and Mason are parties to a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents