One constraint in an LP problem is: 12X + 7Y > 4,000.If the optimal solution is X = 100 and Y = 500,this resource has
A) slack variable of 700.
B) surplus variable of 700.
C) output coefficient of 700.
D) none of the above.
Correct Answer:
Verified