The term force majeure as an event generally excusing contract performance under Tandrin Aviation does not include cost increases of performance,loss of anticipated profits or a general economic downturn.
Correct Answer:
Verified
Q3: In the People's Republic of China,domestic contract
Q4: Specific performance is an equitable remedy requiring
Q5: "Conflict of Laws" in an international setting
Q6: The Convention on Contracts for the International
Q7: The term "trade usage" refers to the
Q9: Money damages for breach of a sales
Q10: U.S.lawyers generally prefer to draft contracts in
Q11: Consequential money damages for breach of a
Q12: Under the CISG,all contracts for the sale
Q13: Parties can "opt out" of CISG application