Which of the following statements is TRUE about velocity?
A) The customer sets the velocity of each scrum period.
B) When a project begins, the senior team members guess the velocity of the team.
C) After a scrum team commits to requirements in a scrum period, it estimates the velocity it can achieve.
D) A team approaches the scrum master to change the order of the requirements to which it has committed.
Correct Answer:
Verified
Q44: Which of the following is NOT considered
Q45: The _ is not the boss but
Q46: Scrum is distinguished from other agile development
Q47: A team uses its _ to determine
Q48: All of the following are principles of
Q50: All of the following are agile development
Q51: Teams assess how it's doing at the
Q52: Higher ranked requirements are completed last because
Q53: Software, information systems, and business processes are
Q54: Overtime the number of requirements that can
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents