Multiple Choice
Present Value of 1 Future Value of 1
Present Value of an Annuity of 1
Future Value of an Annuity of 1
A company is considering investing in a project that is expected to return $350,000 four years from now.How much is the company willing to pay for this investment if the company requires a 12% return?
A) $55,606
B) $137,681
C) $222,425
D) $265,764
E) $350,000