Sanchez Company's Output for the Current Period Was Assigned a $400,000

Question 104

Multiple Choice

Sanchez Company's output for the current period was assigned a $400,000 standard direct labor cost.The direct labor variances included a $10,000 unfavorable direct labor rate variance and a $4,000 favorable direct labor efficiency variance.What is the actual total direct labor cost for the current period?


A) $414,000.
B) $386,000.
C) $394,000.
D) $406,000.
E) $410,000.