A company provided the following direct materials cost information.Compute the cost variance.
A) $2,500 Favorable.
B) $78,250 Favorable.
C) $78,250 Unfavorable.
D) $80,750 Favorable.
E) $80,750 UnfavorablE.Actual cost $888,250 - Standard cost $810,000 = $78,250 U
Correct Answer:
Verified
Q43: A company's flexible budget for 10,000 units
Q49: An analytical technique used by management to
Q50: An internal report that helps management analyze
Q50: Static budget is another name for:
A) Standard
Q52: Identify the situation below that will result
Q54: A flexible budget may be prepared:
A)Before the
Q55: A company's flexible budget for 12,000 units
Q56: Sales variance analysis is used by managers
Q57: A flexible budget performance report compares the
Q58: In this type of control system,the master
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents