Assume That Funtime Corp - What Percentage Is Playground Complete?
A) 62

Question 42

Multiple Choice

Assume that Funtime Corp. has agreed to construct a new playground for Durrey County for $2,300,000. Construction of the new playground will begin on March 17, 2012 and is expected to be completed in August 2013. At the signing of the contract Funtime Corp. estimates that the it will cost $1,600,000 to build the playground.
At the end of 2012 Funtime provided the following information about the project:
Costsincurred Estimated costs  Yearto date  remaining2012$1,000,000$800,000\begin{array}{llcc}& \text {Costsincurred } & \text {Estimated costs } \\\underline{ \text { Year} }& \underline{\text {to date } } & \underline{\text { remaining} }\\2012&\$1,000,000&\$800,000\\\end{array}
- What percentage is playground complete?


A) 62.5%
B) 43.5%
C) 55.6%
D) 50.0%

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents