A 14-week construction activity requires a crane that rents for $1,000 per week and a crew of general laborers that costs $5,000 per week.In order to complete this activity within 10 weeks,you must hire additional general laborers at a cost of $2,000 per week.What is the slope for this activity?
A) $0 per week
B) $1,000 per week
C) $2,000 per week
D) $6,000 per week
Correct Answer:
Verified
Q28: Which of these approaches will NOT accelerate
Q37: The two primary drawbacks to the use
Q38: A finish to start lag delay is
Q39: Use the Gantt chart and the activity
Q40: Activity X has the start to finish
Q43: Use the Gantt chart and activity list
Q44: One reason for crashing a project is:
A)the
Q45: Use the Gantt chart and activity list
Q46: Use the Gantt chart and the activity
Q47: Use the Gantt chart and activity list
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents