In applying the principle of common cause variation to the theory of CCPM,it is important to:
A) not make adjustments to projects when the variation in project performance lies within the range of common-cause variance.
B) immediately call meetings for all key stakeholders if common cause variation is detected.
C) include special cause variation in project risk simulation since there is a chance it may occur.
D) perform risk management on aggregated project risks.
Correct Answer:
Verified
Q17: Critical Chain Project Management is based on
Q18: Even though they know that their project
Q20: Both positive and negative variations are usually
Q21: A(n)_ refers to a safety margin separating
Q23: In classic project management,activity durations are estimated
Q24: Delays in project activity are known as
Q25: According to CCPM:
A)using a point estimate for
Q26: A(n)_ refers to a safety margin that
Q27: The _ Theorem states that if a
Q95: The legal department is needed to review
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents