XYZ project organization has one workstation that is capable of generating the drawings that their clients study before accepting XYZ's bid.XYZ is currently in the midst of three proposal projects and knows exactly when it will need to use the workstation.All other work to be done,both before and after the workstation is used,is scheduled such that it flows to the workstation and keeps it busy.Resources used after this step are less critical;so while the subsequent work and resources are important,they aren't viewed with the same reverence as the workstation.This is an example of:
A) identifying a constraint.
B) elevating a constraint.
C) subordinating a system.
D) exploiting a constraint.
Correct Answer:
Verified
Q35: Which of the following is an example
Q36: The first step in TOC methodology is
Q37: CCPM advocates putting off non-critical activities as
Q38: The _ syndrome describes the tendency to
Q39: In applying the principle of common cause
Q41: All five members of a project team
Q42: If a project activity experiences positive variation:
A)the
Q43: All five members of a project team
Q44: All five members of a project team
Q45: The student syndrome of wasting extra safety
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents