The one factor that earned value management considers that an S-curve does not include is performance.
Correct Answer:
Verified
Related Questions
Q58: Duration (weeks) Q59: Use the earned value table to Q60: A project manager can calculate the projected Q61: The earned value of a project is Q62: Geoff coolly surveyed his earned value Q64: Your organization is in the midst of Q65: Five weeks in the semester you have Q66: Each activity contained a series of milestones Q67: What is the cost variance of Q68: Use the earned value table for