A project manager is using the payback method to make the final decision on which project to undertake.The company has a 10% required rate of return and expects a 4% rate of inflation for the following five years.What is the discounted payback of a project that has cash flows as shown in the table?
A) 3.4 years
B) 2.6 years
C) 5.0 years
D) 4.2 years
Correct Answer:
Verified
Q35: Which statement about the Analytical Hierarchy Process
Q49: Which of these statements about valuation models
Q56: A project manager is using the internal
Q59: Which statement regarding project selection is best?
A)Organizational
Q60: Which statement regarding project selection and screening
Q62: Which of these statements about internal rate
Q63: The pairwise comparison approach:
A)is a method to
Q65: The profile model plots a graph on
Q67: A project manager is using the payback
Q68: The efficient frontier in project management is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents